Skip to main content

Project Updates

PSFPD Fire Station & Community Center Dedication April 29, 2018

The Pinewood Springs community gathered on April 29, 2018  to dedicate the new Fire Station and Community Center! Wonderful weather, new & old friends, tours of the facility and cupcakes were enjoyed by all.

PSFPD Fire Station & Community Center nearing completion!

Join us for the PSFPD Fire Station & Community Center Dedication Event on Sunday, April 29 at 2pm!

Photo of a fire station

PSFPD Fire Station & Community Center Project Phase 2

Community members pitch in.

 

PSFPD Fire Station & Community Center Project

Phase 2 underway

Phase 2 of the Fire Station & Community Center Project, a remodel of the existing Fire Station is underway in June 2017.

Photo of a building being constructed

PSFPD Fire Station & Community Center Project              

Phase 1 nearing completion

Phase 1 of the Fire Station & Community Center Project, a new 4-bay garage, is nearing completion. Our volunteer firefighters have moved equipment and temporary operations into the new structure in preparation for Phase 2.

Photo of people inside a fire station
Photo of a fire truck in a garage

Phase 2 Contract Awarded

The PSFPD Board of Directors awarded the Pinewood Springs Fire Station & Community Center Remodel (Phase 2) to Cactus Ridge Construction in early March 2017.

Phase 1 Construction Continues

Erecting the 4-bay garage structure in March 2017.

Photo of a building being erected

 Construction continues in February 2017; pouring foundation walls.

Photo of workers at a construction site
Photo of a construction site

 

 

 

PSFPD Fire Station & Community Center Project Phase 2 RFP issued

On February 1, 2017 PSFPD issued a public RFP for the Fire Station and Community Center Project Phase 2: remodel of the current building.

Community Center Restricted Access

The construction team has decided to close all public access to the community room at the Fire Station effective February 1, 2017.

Progress on the new garage building is proceeding ahead of schedule. The grading is complete, and excavation for the foundation for the new garage is underway. Shortly thereafter, concrete work will begin. As you have probably seen, the terrain along the west edge of the existing building is changing on a daily basis. The black insulating tarps are very slippery with snow on them. The team feels it’s too dangerous for community members and the public to be walking around the construction site, especially at night.

Alternative Meeting Space Available

The Pinewood Springs Community Church has offered use of the Community Church Fellowship Hall for meetings normally held at the Fire Station Community Room. Fire Board, Road Board, Water Board and PSPOA meeting dates will automatically be moved to the Church Fellowship Hall; same times & dates. If you have any questions, please contact Gabi at 303.823.5345.

PSFPD Fire Station & Community Center Phase 1 Construction underway

Construction and prep work are underway, with a targeted completion timeline for Phase 1 in Spring 2017.

Photo of a bulldoser and a building

 Working with Pinewood Springs Water District on new water line in Dec 2016.

Photo of a construction site

 Phase 1 Contract Awarded in mid-November

Following a public bid process, the Fire Board awarded the PSFPD Fire Station & Community Center Phase 1 contract for excavation & construction of a 4-bay garage to Colorado-based Schauer Construction on November 16, 2016.

The 4-bay garage will be built immediately adjacent to our current Fire Station (digital concept drawing below). Prep work is underway, with Phase 1 construction slated to begin in January. The targeted completion timeline is Spring 2017.

Emergency Services will remain operational through all construction phases.

Phase 2 of the project will be an extensive remodel of the existing Fire Station structure, targeted to begin in 2017. This 2-phased approach allows the Fire Board to achieve our community goals and stay within budget.

Photo of a building

PSFPD Fire Station and Community Center New RFP issued

On Sept 29, 2016 PSFPD issued a public RFP for the Fire Station and Community Center Project.

Update on RFP process for Fire Station and Community Center Project

As reported in early August, round 1 of project bids were rejected by the Fire Board as unacceptable due to severely inflated construction costs seen across Colorado. Based on these market conditions, the Fire Board and project teams are working closely with the county and DOLA on a hybrid project plan: a 4-bay garage addition and refurbishing the existing structure.

PSFPD Fire Station and Community Center Project RFP issued

On June 16, 2016 PSFPD issued a public RFP for the Fire Station and Community Center Project.

DOLA Grant Update

On April 6, 2016 we learned that our community will be granted full budget matching funds of $406,000 for the PSFPD Fire Station and Community Center Project. A BIG thank you to our community for your ongoing support, many generous contributions and hundreds of volunteer hours.

November 2015 Election Update

The mill levy to provide partial funding for the PSFPD Fire Station & Community Center project was officially certified by Larimer County on November 18th. The count was 203 yes, 197 no. The response rate was 68% of 587 ballots issued. The Fire Board and Construction Project Team submitted our DOLA grant application for matching funds on December 1, 2015 and received notice of the award in early April.

Our Fire District

The Pinewood Springs Fire Protection District provides 24 x 7 x 365 service for the Pinewood Springs Community and highway US-36 from mile marker 8.5 to mile marker 12.75. Those 4+ miles include Dead Man’s Curve, a notorious section of mountain highway.

Annually, over 3 million vehicles pass through Pinewood Springs (on US-36) on their way to scenic Estes Park and Rocky Mountain National Park – a 30% vehicle increase since 1999 – resulting an ever increasing number of vehicle response calls. In addition, the community population has grown from 123 in the early 60’s to almost 1000 today, leading to more medical and fire calls. As a result, the fire department continues to recruit, train and equip firefighters.